Outage: Internet services (solved)

Dear customers,

We have experienced an outage with internet services in the Wavre / Charleroi areas. The outage is currently under investigation by our NOC team. Further updates will be released as soon as possible.

Please find all details below:

Start: 2016-11-3 16:15*
End: 2016-11-3 16:40*
Duration: 25 minutes
Impacted services: All services
Affected Areas: 071GIL: 010, 060, 064, 065, 067, 068, 069, 071

Update 4/11/2016 10:15: the solution has been found, proximus is resetting the communication paths one by one, lines should be starting to get back online one by one.  We advise you to reboot your router if you do not see any changes in the status of your connection after 30 min.

Update 4/11/2016 8:08: some lines remain offline, rebooting doesn’t seem to help. These cases are under investigation, we do our utmost to have the issue resolved.

Update 3/11/2016 21:45: Root cause found, works were performed to extend our capacity, and a configuration mistake was made by proximus. The configuration is adapted and we recommend rebooting your device to regain internet access.

Update 3/11/2016 17:00 Recovery of offline customers is our top priority. A lot of the affected lines are back up, but there are still some down.

We apologize for the inconveniences.

Best regards
The edpnet team

*All times are listed in CET, Central European Time


Maintenance planned on 31/10/2016 – impacted services: Telephony

Dear customers,

Edpnet has planned a maintenance in order to upgrade the software of our voice switches.

No impact is expected, but this maintenance may affect your services.

Please find all details below:

Start: 2016-10-31 05:45*
End: 2016-10-31 05:52*
Duration: 7 minutes
Impacted services: All Telephony services
Affected Areas: BE

We apologize for the inconveniences.

Best regards
The edpnet team

*All times are listed in CET, Central European Time


Maintenance planned on 07/10 – impacted services: All telephony services (closed)

Update 07/10/2016 – 02:48:

Dear customers,

Last night’s maintenance was successfully completed. Redundancy tests were performed by bringing down each voice switch.

One switch failed during these tests and corrective measures were taken. After these measures all tests were conducted again and finished 100% successfully.

Best regards
The edpnet team

 

Initial post:

Dear customers,

Edpnet has planned a maintenance in order to provide full redundancy on our telephony services in the future.

This maintenance may affect your services.

Please find all details below:

Start: 2016-10-07 01:00*
End: 2016-10-07 03:00*
Duration: Approx. 60 – 90 minutes
Impacted services: All telephony services
Affected Areas: All

We apologize for the inconveniences.

Best regards
The edpnet team

*All times are listed in CET, Central European Time


Info: Overview of the latest outages and solutions

Dear customers and partners,

As you all know, edpnet has gone through a number of serious outages lately. The initial power outage exerted a huge impact on our core infrastructure which caused, unfortunately, much tension to our customers and ourselves. We understand that it is hard to justify the confidence in such circumstances and want to apologize for all inconvenience. Strong measures have already been taken to reduce a risk of further outages and guarantee the stability of our services.

As open communication is very important for us, we would like to provide you with a detailed overview of what exactly happened and what we have done/are going to do to prevent these situations in future and improve our service. Please, find the overview below.

Monday 26/09/2016 4:49: the data center of edpnet Sint-Niklaas lost power, UPS system and power generator failed.

Monday 26/09/2016 10:19: the power was restored, systems were back online. Due to the many issues to get the power online, we provided a backup power feed from our office power feed to the most critical systems

Monday 26/09/2016 11:00: mail load balancers were dead, probably due to intermediate power cuts. These devices were replaced.

Monday 26/09/2016 20:00: the power was lost again in the data center, critical applications such as voice services and main router were still running. The interruption caused an issue on incoming calls.

Monday 26/09/2016 20:15: The root cause of the power issue was found, the UPS itself caused the power cuts. We bypassed the UPS and restored power.

Monday 26/09/2016 21:30: incoming calls were running fine again.

After the power cut, we noticed some strange behavior on our Voice switch 2, several maintenances were performed to have the system stable again, no more issues were noticed after these maintenances.

Sunday 2/10/2016 23:30: a DDoS attack starts which causes connectivity problems.

Monday 3/10/2016 9:30: The DDoS target is found and disabled. Connectivity restored.

Tuesday 4/10/2016 0:00: Planned maintenance to replace the broken UPS, and installing an external bypass system so future UPS maintenance shouldn’t give an interruption.

Wednesday 5/10/2016 7:44: A database issue occurred on Voice switch 2.

Wednesday 5/10/2016 8:06: The database is restored, voice is operational.

Thursday 6/10/2016 1:46: Voice switch 2 crashes, is completely unavailable. Voice switch 1 isn’t taking over causing voice calls not to arrive, and outgoing calls not to be made.

Thursday 6/10/2016 6:43: manually switched all voice traffic towards Voice switch 1, incoming and outgoing calls seem to work fine.

Thursday 6/10/2016 9:00: complaints arrive that no incoming calls are possible again, it seems Voice Switch 1 only receives 50% of the incoming calls

Thursday 6/10/2016 10:57: restored Voice switch 2 on spare hardware, all calls are arriving no more voice issues.

Thursday 6/10/2016 11:30: Proximus and supplier found the issue with the failing redundancy of the voice switches, a new maintenance will be planned soon to make the necessary improvements.

List of improvements to be made:

  1. UPS replacement (done)
  2. External bypass system to avoid outage due to UPS works (done)
  3. Move certain critical services to our data center in Interxion Brussels (ongoing)
  4. Install a permanent B-power feed in our data center in Sint-Niklaas (ongoing)
  5. Adapt voice service for correct redundancy (done)

 

If you have any questions or remarks left, please, do not hesitate to contact us.

Best regards
The edpnet team


Outage: Voice services (solved)

Dear customers,

We have experienced an outage with incoming voice traffic. The outage has been solved.

Please, find the details below.

Start: 2016-10-06 01:46*
End: 2016-10-06 10:57*
Duration: 9:11
Impacted services: All voice traffic
Affected Areas: all areas

Update 11:26: all voice services are restored and are fully operational. There are still issues with redundancy, but we are working on this with the highest priority. No further unannounced voice issues should occur.

We apologize for the inconveniences.

Best regards
The edpnet team

*All times are listed in CET, Central European Time


Outage: Voice issues (closed)

Dear customers,

We are experienced an outage with some voice services. A database issue occurred probably due to the power issues last Monday. The database has been restored.

Please find all details below:

Start: 2016-10-05 7:44*
End: 2016-10-05 8:06*
Duration: 22 min
Impacted services: Voice services
Affected Areas: All Areas

 

We apologize for the inconveniences.

Best regards
The edpnet team

*All times are listed in CET, Central European Time


Issue: Internet connectivity issues

Dear customers,

We have experienced a DDoS attack. The attack is under investigation by our NOC team. The DDoS target has been found and disabled. The issue is solved. We are researching how to mitigate future attacks.

Please find all details below:

Start: 2016-10-02 23:30*
End: 2016-10-03 09:30*
Duration: 10 hours, intermittent disconnects
Impacted services: All DSL services
Affected Areas: 03WIB, 03TEM, 03KAP, 03CEN, 11NER, 11TRU, 11HSW, 16HSR, 89GEN, 03WIL, 13TES, 14BAL, 11HSZ, 03BOO, 03KON, 14HER, 14TUR, 16AAR

 

We apologize for the inconveniences.

Best regards
The edpnet team

*All times are listed in CET, Central European Time


Maintenance planned on 04/10/16 – impacted services: cloud telephony and colocation service

Dear customers,

Edpnet has performed a maintenance last night in order to install new UPS-device in our data-center in Sint-Niklaas. This has been done to avoid power loss in the future.

This maintenance is finished successfully.

Please find all details below:

Start: 2016-10-04 00:00 AM*
End: 2016-10-04 02:00 AM*
Duration: 2 hours
Impacted services: Cloud telephony and colocation service
Affected Areas: all

 

We apologize for the inconveniences.

Best regards
The edpnet team

*All times are listed in CET, Central European Time


Outage: mail

Dear customers,

We have experienced an outage with our mail server. For now all mail systems are running again.

Please find all details below:

Start: 2016-09-27 15:00*
End: 2016-09-27 15:42*
Duration: 42 minutes
Impacted services: mail
Affected Areas: all

Update 27/09/2016 – 16-00: Mail service is fully restored.

We apologize for the inconveniences.

Best regards
The edpnet team

*All times are listed in CET, Central European Time


Power outage at edpnet colocation

 

Dear customers,

We have experienced an outage at our colocation in Sint-Niklaas. For now all systems are running again.

Please find all details below:

Start: 2016-09-26 07:00*
End: 2016-09-26 16:50*
Duration: Telephony and web services: 3 hours

Mail: 9 hours 50 min

Impacted services: All telephony services, mail, web services
Affected Areas: All areas

Update 26/09/2016 – 21:30: Incoming voice should be fine now as well.

Update 26/09/2016 – 20:00: We hit the same issue as this morning, power outage of the collocation in Sint-Niklaas, probably due to a faulty UPS, we now bypassed the UPS and are starting all services again.
We added extra protection for the main router and our telephony system so no impact was expected there, but due to a strange coincidence our incoming voice also appears to be impacted by a fiber cut in Brussels that forced a reroute.

Update 26/09/16 – 16:50: High mail latency is solved.

Update 26/09/16 – 14-00: Webmail service is restored, but some customers still could face mail latency about 1 hour due to the huge amount of mails to be delivered on our servers.

Update 26/09/2016 – 12:30: Webmail is currently down in order to avoid too much delay and heavy traffic towards our backup mail system. 

Update 26/09/2016 – 10:19: All impacted services have been restored and are running again. Our mail relays are clearing out their backlogs.  We expect normal mail traffic flow to be resumed soon.

We apologize for the inconveniences.

Best regards
The edpnet team

*All times are listed in CET, Central European Time